I-74 work continues next week in Decatur County
Ramp closures are scheduled to begin next week at the State Road 3 / I-74 interchange (Exit 134) in Greensburg. Crews with Dave O’Mara Contractor Inc. will complete milling and paving on four ramps to and from I-74.
The following ramps will be closed beginning at 9 a.m. on Monday, Oct. 21, weather permitting:
S.R. 3 SB to I-74 EB
S.R. 3 NB to I-74 WB
I-74 WB to S.R. 3 SB
I-74 EB to S.R. 3 NB
All ramps are expected to reopen by end of day on Monday, October 28. Start and end dates will be shifted in the event of bad weather. The detour for the closures will follow U.S. 421 at Exit 132 to S.R. 3 in Greensburg.
Also beginning Monday, the ramp from southbound State Road 3 to westbound I-74 is scheduled to close for a separate asphalt patching project in Decatur County. The closure is expected to last up to ten days, weather permitting. Lane closures will also be in effect on I-74 from State Road 3 at Greensburg to Exit 123 (St. Paul / Middletown) through late November into early December.